半自動貼標機
Your current location : Home >> News >> Technical Knowledge

Commissioning blister packaging machine start-up operation steps and principles explained

2019-05-06
times

Commissioning blister packaging machine start-up operation steps and principles explained


(1) re-check the PVC, aluminum foil in place according to the installation requirements, the moving parts of no foreign objects, and ensure that the platform on the PVC no foreign objects, no red light on the operating simulation panel.


(2) Press the main motor button, the main motor indicates that the green light is on, and wait for 5-7 seconds (at this time, each work is in a completely open state and does not move at this time, and the mobile feed air clamp is at the nearest end, these two states and positions are the commissioning origin).


(3) press the run button while indicating that the green light is on, the equipment blister packaging machine. At this time, each workstation to maintain no action, mobile air clamps forward movement, mobile air clamps drive PVC through the heating plate (see Note ⑤ for details of the upper and lower heating plate gap adjustment), PVC by I heat, reaching the forming station, the feed mechanism is at the farthest end. The forming station is completely closed, the PVC is pressed, and a signal is given by the micro switch, and the solenoid valve is operated to give compressed air, and the PVC is blown into the same blister as the forming plate, which is the process of positive pressure forming of PVC blister.


(4) Move the air clip to continue to drive the PVC forward, when the first molding blister reaches the hot laminate, look at the number displayed by the counter, this number is the number of steps of the - cycle (equipment in the commissioning alignment process often use this number. Alignment means that when the forming bubble cover reaches the hot lamination, the forming bubble cover can enter the hot lamination bubble exactly. For details of the alignment adjustment process, see Note 6).


(5) The moving air clamp drives the PVC forward again and reaches the punching and cutting knife, and the punching station closes and the drug plate is punched down. After the board is punched down, its front and rear position should be symmetrical (see Note 7 for the adjustment method). The remaining waste is driven by the waste motor and wrapped to the waste section collection station. At this time, the equipment. A complete motion cycle is completed, the equipment in the running state intermittently and continuously complete this process.


(6) When the feeding mechanism of the equipment is at the farthest end, press the stop button and the green light of operation goes out. The farthest end is the position where the mobile air clamp runs to the farthest point from the threaded top bar. The machine stops at the fixed point position. The fixed point position means: controlled by the signal axis, each workstation is fully opened to the maximum position, and the feed mechanism returns to the farthest end.


 (7) Clean up the environment and equipment to meet CMP requirements. Put the medicine into the hopper or fabric tray, put down the universal downcomer, open the universal downcomer changeover switch to make the universal downcomer vertical brush and roller brush rotate normally. Press the run button, blister packaging machine start to run a cycle to confirm accurate alignment, and then trigger the oscillation changeover switch, so that the oscillation disk vibration drug into the molding bubble inside the device, into normal production operation.


url: http://m.commonsfanghard.com/en/news/458.html

Products

News

深圳市昌浩慧豐實業(yè)有限公司



Shenzhen Changhao Huifeng Industrial Co.

9F, Zhengke Times, No.17, Industrial Road 1, Da Wang Shan, Shajing Street, Baoan District, Shenzhen

Copyright@2023粵ICP備15020808號